Energy Audit

Wipro Technologies, Bangalore

1999 -2003, Repeat jobs.

PROJECT DETAILS
At 10-facilities across Bangalore. IT/Software development and data centers. Energy Audit. Energy and DG SEGR analysis
RESULTS ACHIEVED
7% Energy Savings verified with NO-COST implementation with several building's HVAC system through process optimization. Shared fees through performance contracting energy savings.

Infosys Technologies Limited, Bangalore

2003

PROJECT DETAILS
Software development center with four building modules at Electronics City, Bangalore
RESULTS ACHIEVED
14% Energy Savings verified with NO-COST implementation with the building's HVAC system through process optimization.

Gulmohar Paper Ltd, Calcutta

2000

 

PROJECT DETAILS
Writing, Printing and Packaging Paper Manufacturing Plant.
RESULTS ACHIEVED
Energy savings verified. Energy and total power management

Emami Paper Limited, Balasore Orissa

2000-2006, Repeat jobs

PROJECT DETAILS
Writing, Printing and Packaging Paper Manufacturing Plant.
RESULTS ACHIEVED
Energy Savings verified at NO-COST implementation

Sunil healthcare Ltd, Alwar Rajasthan

2010 -2012, Repeat jobs.

 

 

PROJECT DETAILS
20MPD empty gelatin capsules plant. Major energy & Diesel fuel savings were achieved through process optimization. HVAC&R hot water boilers were switched off and instead condenser hot water with little AHU modifications were used for Humidity control.
RESULTS ACHIEVED
9% Energy Savings verified at NO-COST implementation. HVAC&R optimization through process optimization implementation and energy consultancy.

Lake Chemicals Ltd, Bangalore

1998

PROJECT DETAILS
Bulk drug manufacturing facility.
RESULTS ACHIEVED
5% Energy Savings verified at NO-COST implementation

Taj Gateway Hotel Bangalore

1997-2004, Repeat jobs.

PROJECT DETAILS
Third party test Screw chillers efficiency test. BMS efficacy test.
RESULTS ACHIEVED
9% Energy Savings verified at NO-COST implementation

Mercure Homestead Residences, Accor Hotels, Bangalore

2010

PROJECT DETAILS
Air cooled air conditioning system installed. 126 rooms, each between 400 -854 sft size, 125,000sqf built-up area including inc.12% park&M.
RESULTS ACHIEVED
6% Energy Savings verified at NO-COST implementation

Sheraton Brigade, Bangalore

2012

PROJECT DETAILS
230 rooms, 600,000 SQF built-up area (incl.33% park and maintenance). 20-Floors (3B+1G+1M-5th+15). 1.4mw maximum demand.
RESULTS ACHIEVED
6% Energy Savings verified at NO-COST implementation.