Lighting ballast failure

EID Parry India Ltd, Corporate bldg

2012- 2017 Repeat Jobs. EID Parry is a heritage building of 1932 with 6 Story, 250,000 Sq. built up space.

PROJECT DETAILS
Head Office of Murugappa conglomerate that accommodates 1300 employees. Local Utility mandated harmonic limits. In-addition was facing failures with air conditioning compressor motors, transformer, Lighting ballast failure, computer cards and SMPS.
RESULTS ACHIEVED
Installed 750A and 646A tuned harmonic filters and that resolved all harmonic failures and limited harmonic distortions within CEA 2007 and IEEE 519 norms of local the utility.

Eliminate Electrical Failure

Electrical Failure

Abstract: An Electrical Arc Furnace near a hyperactive railway traction line was facing electrical failure from an unusual power quality harmonic distortion problem. The Gigantic 22kA copper bus bar used to overheat visibly red-hot, vibrate audibly loud loosening nuts and bolts and wear out affected plates.