Turbo energy Ltd, Paiyanoor

2013 to 2017 Repeat jobs. Turbo Energy Ltd Paiyanoor, Mahabalipuram.

PROJECT DETAILS
Was facing CNC, UPS & chiller vfd drives electronics card failures, lighting ballast, and motor burning issues and in addition voltage sag (fluctuation) tripping for CNC m/c. Local Utility company/ TNEB mandated limiting harmonics at it 11kv.
RESULTS ACHIEVED
Installed 831A main transformer and a 88A chiller end harmonic filters, mitigated harmonics within IEEE 519 norms, and eliminated all failures.