Encon Harmonic Solution is an inveterate canon of erudition evolved from 500+ projects with 350+ global corporate clients, solving harmonic failure problem. Thanks to your unstinted support since our inception in 1995 and…
Clients
INDUSTRY | PROJECT DETAILS | RESULTS ACHIEVED |
---|---|---|
Metal Copper Vedanta Sterlite Industries Tuticorain, thro' Siemens 2007 |
Copper Smelter and Copper specialities manufacturing plant. | Root-cause analysis for electronic, ct failure and ACB uP relay malfunction in the Furnace and Hot Rolled Mill Section. |
Metal Copper Meta Copper and Alloys Ltd Goa 2006 |
HRM and CRM for Copper & Bronze Specialties manufacturing. Supplied 2sets harmonic filters for 4mva,11/0.575-0.575kV, Dd0yn5, 6.4%, CRM Transformer with ETR-2x 265kw, DTR-2x 265kw, Mill-2x500kw, pay off-1x 65kw DC Motors. 2x 6.3MVA, 33/11kV DG Incomer. | 8% Energy Savings verified with harmonic filter installation. Debottlenecked capacity limitation and enhance production by 25%. |
Metal Casting Pearlite Liners Pune 2001, Maharashtra |
Automotive Casting and induction furnace loads | Harmonic study carried out and report submitted. |
Metal Casting DGP Hinoday Pune 2001 |
Maharashtra Automotive casting plant with 2nos each 6ton induction furnace | Harmonic study carried out and report submitted. |
Metal Casting Amforge Industries Pune 2001, Maharashtra |
Induction Furnace Casting and Forging plant | Harmonic study carried out and report submitted. |
Metal Casting Ammarun foundries, Coimbatore 2013 |
Casting 300molds per hour. Induction Furnaces 2sets 1.5ton and 1set 2.0ton capacity and Auto-Casting machine | Power quality and harmonic analysis carried out and report with recommendations submitted. |
Metal Aluminium Indian Aluminium Company, Belgaum 2001 |
Alumina manufacturing plant from Aluminium Ore | Power quality and harmonic analysis carried out and report with recommendations submitted. |
Metal ACSR Vedanta, Sterlite Technologies Ltd. Haridwar 2008 -2010, Repeat jobs. |
Induction furnace, HRM, CRM and ACSR conductor manufacturing Process. Supply 2sets of 4000A variable harmonic filters for 2nos 3150kva, 33kv/430v Transformers. | Energy Savings verified with harmonic filter installation. Debottlenecked capacity limitation and enhanced production capacity. |
Metal ACSR Sterlite Power Transmission & Technologies Ltd 2007 -2011, Repeat jobs. Sterlite Power Transmission and Sterlite Technologies Ltd at Silvasa |
Supply 2000A,1000A and 500A variable harmonic filters for 2000kva, 1500kva and 750kva transformers. To solve voltage fluctuation tripping problems and frequent equipment failures. | 9% Energy Savings verified with harmonic filter installation. Debottlenecked capacity limitation and enhance production by 25%. |
Metal ACSR Galaxy Transmission Sangli 2013, Maharashtra |
Rolling mill 1,000tpm and Conductor 1,500tpm capacity manufacturing plant | Power quality and harmonic analysis carried out and report with recommendations submitted. |
IPP Power Plant Suryadev alloys & power, Gummidipoondi 2013 Chennai |
80mw 2sets thermal power plants with air-cooled condensers. SEC=0.75ton/mw of coal, PP Aux=8%; 2x330tph boiler, 95kg/cm2, 540oC. | Trouble shooting study carried and and report with recommended measures submitted. |
HVAC&R Johnson controls Ltd Bangalore 2008 -2009, Repeat jobs.
|
Air conditioning AMC maintenance for 2x 200TR Centrifugal Chiller and with its high and low side Air-conditioning system | O&M |